ROADWAY IMPROVEMENTS: Prince Place, Ash, Locust, Worthington, Burley, Maple, Fidelity/Endicott from June 16-June 19

Posted on June 15, 2017


ROADWAY IMPROVEMENTS: Prince Place, Ash, Locust, Worthington, Burley, Maple, Fidelity/Endicott from June 16-June 19 (weather permitting).

11 Prince Place
Prince Place and Centre Street
7 Ash Street
11 Ash Street
Fidelity on Endicott Street
160 Locust Street
12 Worthington Ave
6 Worthington Ave
3 Burley Street
17 Burley Street
526 Maple Street
332 Maple Street
312 Maple Street

The Town of Danvers will begin making roadway improvements to the above areas of these streets. The existing roadway surface will be Milled and Paved. This process takes two days to complete. Vehicles will not be allowed to park along the roadway between 7:00 AM and 5:00 pm. In the event of rain, this work will be performed the following day.